http://www.mercurynews.com/pge/ci_21759694/pge-san-bruno-explosion-fire-should-pay-most-pipeline-repair-costs
Friday's decision by Judge
Maribeth Bushey, which requires full commission approval to go into
effect, took issue with major parts of PG&E's plans to improve
its pipeline system, including the company's proposal to bill its
customers for the vast majority of the work. She rejected the company's
request to bill 90 percent of the cost to ratepayers, arguing that
PG&E's "shareholders should not be shielded'' from the costs
because the company's "poor management decisions" allowed its natural
gas system to deteriorate.